The city announced that hillside restoration at Wailupe Valley along Leighton Street will begin next week.

The $151,136 project contracted to Close Construction, Inc. begins on Monday, Sept. 28, with an expected completion date of Friday, Dec. 18.

The work schedule will be from 8:30 a.m.-3:30 p.m., Monday through Friday. Traffic control measures will be implemented along Leighton Street while work is performed. Motorists are reminded to observe and obey all traffic controls, posted signs, and traffic control personnel in the work area.

The project consists of installation of an impervious liner along the base of the existing rock walls to prevent further water from seeping down and potentially accelerating earth movement. The scope of work includes reconstruction of sidewalks, curbs, and retaining walls; replacement of chain link fence; and installation of new polypropylene liner.

Close Construction, Inc. is responsible for coordinating local traffic. Call (808) 851-7060 with any concerns.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s